Got Big Water

YouTube
YouTube Channel

Facebook
Facebook Page

Twitter
Twitter Page

Rural Water Supply Operations Seminar
Rural Water Supply Operations Seminar

Water Supply Officer Seminar
Water Supply Officer Seminar

Relay Pumping With Large Diameter Hose
Relay Pumping With Large Diameter Hose

Dry Fire Hydrants Seminar
Dry Fire Hydrants Seminar

Dry Fire Hydrant Designs and Installations
Dry Fire Hydrant Designs and Installations

Suction Strainer Flow Test Project:Test Results

Web Counters
Website Visitors
Since
June 22, 2009
3,030,788
Visitors Today
Sep 08, 2024
16



Official PayPal Seal
Dump Site Operations #30 - Be Ready to Dump Multiples
Email Print RSS Facebook Twitter RSS

By President Mark Davis
June 13, 2024

Another simple but important message. When setting up a dump tank operation to flow in excess of 1000 gpm folks need to plan to build out the arrangement to accommodate several tankers dumping at the same time. While effective water transfer operations are probably the more critical item to "keep an eye on," the person in-charge of the dump site needs to also ensure that dumping operations are not restricted to just one tanker at a time. We grabbed this photo from our seminar in Riverton, Connecticut two weekends ago. This four-dump tank operation is supplying a 1600 gpm simulated fireground flow and these three tankers are dumping their water simultaneously. Once the flow exceeded 1300 gpm, just about every time you looked at the operation at least two tankers were dumping their water.

 
Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
GBW Associates, LLC
3178 Cardinal Drive
Westminster, MD 21157

Emergency Dial 911
Phone: 443-398-6619
E-mail: thebigcamel@gotbigwater.com
Copyright © 2024 Firehouse Solutions (A Service of Technology Reflections, Inc.)